Progress report. Newsletter no 13. To find out the works that have been completed this week and also ongoing works at the development at Bretonside.
McLaren Site Office:
Works completed this week include:
Closure of footpath to viaduct completed.
Tubosider attenuation tank installation ongoing.
Retaining wall to RBS perimeter ongoing.
SWW drainage to undercroft commenced.
CSR update with planned events:
We will be delivering our second community site newsletter to local residents and businesses in March and holding a community drop in on site Thursday 8th March from 1-2pm.
We will be holding a mini MOT health check for site operatives on March 5th .
We will be hosting an open doors event with Building Plymouth on 19th March.
To find out more click here