Project Progress:
McLaren Site Office:
Works progressed this week include:
Structural steelwork installation to Zone 2 commenced.
Preparation works to Zone 3 ready for steelwork installation.
Drainage and concrete slab preparation within the viaduct undercroft ongoing.
Bases completed to Zone 5 ready for steelwork installation next week.
Works programmed for the next week include:
Commence installation of structural steelwork to Zone 5.
Continue with drainage to undercroft and preparation for slab pours.
Continue with forming bases to Zone 3 ready for steelwork installation.
Meeting arranged with CTP on Tuesday 10th April to discuss work placement for ex-forces personnel.