Progress report. Newsletter no 16 March 2018. To find out the works that have been completed this week and also ongoing works at the development at Bretonside.

Works progressed this week include:

Structural steelwork installation and groundworks ongoing.
A mini MOT health check for site operatives was held on site, March 5th.
A milestone ceremony was held on site with members of Plymouth City Council and Plymouth Herald.
Our second community newsletter was delivered to the local businesses and a copy emailed to Plymouth Community Homes to distribute to their local residents on How Street.velopment at Bretonside - Plymouth

Works programmed for the next week include:

Continue with installation of structural steelwork.
Prepare Zone 2 ready for steelwork installation.
Concrete pours to RBS retaining wall.
Viaduct undercroft to be grit blasted ready for decoration