Development at Bretonside - Plymouth

Date

Find out about the latest work carried out at the exciting Drake Circus Leisure in May.

Project Progess
Works progressed this week include:
Structural steelwork installation to Zone 5 ongoing.
Lane closure on Exeter Street viaduct commenced.
Intumescent painting of structural steelwork commenced ready for external cladding.
Site visit held with engineering and site management students from Plymouth University.

Works programmed for the next week include:

Continue with installation of structural steelwork to Zone 5.
Continue with intumescent painting to structural steelwork and decoration to undercroft.
Commence external cladding works.
Site visit on Thursday 17th May arranged with students from Mount Tamar Secondary School.

Find out more, click here