Skip to main content

Development at Bretonside - Plymouth

Date

Find out about the latest work carried out at the exciting Drake Circus Leisure recently.

Works progressed this week include:
Structural steelwork installation to Zones 3 and 6 ongoing.
Stud welding to podium level commenced.
Zone 2 roof netted ready for roof lining works..
Plymouth Fire Brigade visited site this week to provide a rescue from height training day for contractors on site.

Works programmed for next week include:
Continue with steelwork installation to Zones 3 and 6.
Continue with roof lining works to the sky bar and commence Zone 2 roof.
Continue with decking and stud welding to podium level.
Students from Lipson Co-op Academy commencing work placements on site