Development at Bretonside - Plymouth

Date

Find out about the latest work carried out at the exciting Drake Circus Leisure recently

Project Progress

Works progressed this week include:

Structural steelwork installation to Zones 4 and 7 ongoing.
Section 278 works ongoing on St Andrew Cross and nearing completion.
Decking commenced to the Plant Deck and Sky Bar.
Cladding commenced to the Bretonside elevation.

Works programmed for next week include:

Continue with steelwork installation to Zone 4 and 7.
Continue with the roof lining works to Zone 4A.
Continue with decking and stud welding to the Sky Bar and Plant Deck.