Bretonside Development Progress Update
Find out about the latest work carried out at the exciting Drake Circus Leisure recently.
Works progressed this week include:
- Paving and landscaping completed to St. Andrews roundabout
- Dry lining ongoing to IMAX auditorium and commenced in auditorium no.2
- Decking completed to podium, auditoria levels and commenced in Zone 4
- Concrete pours to lower car park, podium and auditoria levels.
Works programmed for next week include:
- Complete external panelling to Bretonside elevation
- Open pedestrian crossing at St.Andrews roundabout
- Continue with Dry lining works to the IMAX auditorium
- Continue with concrete pours to lower car park level.
To find out more, click here