Sherford
Sherford, Devon, PL9 8AX
The LPAs support the implementation of the existing planning permissions and strategic masterplan relating to the strategic development proposals for the Sherford new community. Provision is made for 5,500 new homes 4,254 of which are anticipated to be delivered within the plan period) and 67,000 sq.m. of employment floorspace. Any significant changes to the approved schemes will need to be supported by a revised strategic masterplan.
Site Information
SITE AREA: 490 ha (121ha residential, 200ha Community Park)
OWNERSHIP: Sherford consortium (Bovis, Taylor Wimpey, Linden)
Existing Use: Greenfield
Joint Local Plan Allocation PLY48/49
5500 homes, 67000sqm of employment, 3 local centres, P&R, 3 primary schools, secondary school, health and community facilities, and sports facilities including a sports centre.
PLY49 – 200ha Community Park
DELIVERY TRAJECTORY: 4254 homes by 2034
Development Progress
Outline consent granted 2013
Two significant S73 applications 2017 & 2018
Phase 1.1 under construction– 610 consented, 480 commenced, 300 occupied.
Phase 1A (205 units) consented
Primary School 1 (first phase) completed and 141 enrolled
1st phase of Main Street and HQPT link (including upgrades to Deep Lane and Stan X completed. Interim Main St phase 2&3 commenced
63ha of Community Park open
Plymouth City Council Next Steps
Phase 1B approved Sept 2019 (428 homes + Community phase 1B)
Local Centre scoping and application Autumn 2019
Marketing Board, Design Code/Brief + RM application for Commercial area due Autumn 2019
Leisure Centre – application winter 2019
S106 compliance + delivery of community facilities (GP surgery, pharmacy, police hot desk, youth centre)
Establish Community Trust
Funding opportunities for infrastructure
Contact
If you would like to find out more information about this development, please get in touch.